PWD Manual Test – The Kerala PWD Manual


The Kerala PWD Manual
Date of Examination :05-09-2019

Question1:-Who is in control of the main executive unit of PWD?
        A:-Chief Engineer
        B:-Superintending Engineer
        C:-Executive Engineer
        D:-Assistant Executive Engineer
        Correct Answer:- Option-C
Question2:-The work of PWD is carried out through how many main wings
        A:-5
        B:-3
        C:-4
        D:-2
        Correct Answer:- Option-A
Question3:-Who controls the Establishment matters in PWD?
        A:-Administrative Officer
        B:-Chief Engineer (Administration)
        C:-Dy. Chief Engineer (Administration)
        D:-Chief Administrative Officer
        Correct Answer:- Option-B
Question4:-Which rank of officer heads the environment cell of PWD?
        A:-Executive Engineer
        B:-Chief Engineer
        C:-Superintending Engineer
        D:-Environmental Officer
        Correct Answer:- Option-A
Question5:-What is KHRI
        A:-Kerala Highway Research Institute
        B:-Kerala High Rise Building Institute
        C:-Kerala Human Resource Institute
        D:-Kerala Health Research Institute
        Correct Answer:- Option-A
Question6:-Which department is to be consulted for repairs of vehicles and machineries?
        A:-PWD
        B:-Irrigation
        C:-KSRTC
        D:-Motor vehicles department
        Correct Answer:- Option-B
Question7:-Who Plans, organise and coordinate works based on budget allocations?
        A:-Executive Engineer
        B:-Dy Chief Engineer
        C:-Finance officer
        D:-Chief Engineer
        Correct Answer:- Option-D
Question8:-Who scrutinize budget estimates and furnish proposals to government?
        A:-Chief Engineer
        B:-Chief Technical Examiner
        C:-Administrative Officer
        D:-Finance Officer
        Correct Answer:- Option-A
Question9:-Who is to test check 10% of value of works beyond the power of Asst Exe Engineer
        A:-Chief Engineer
        B:-Superintending Engineer
        C:-Executive Engineer
        D:-Assistant Engineer
        Correct Answer:- Option-C
Question10:-Who is in control of a Sub division?
        A:-Assistant Engineer
        B:-Assistant Executive Engineer
        C:-Executive Engineer
        D:-Superintending Engineer
        Correct Answer:- Option-B
Question11:-Who is responsible for making arrangements for maintenance works?
        A:-Executive Engineer
        B:-Asst Exe Engineer
        C:-Chief Engineer
        D:-Assistant Engineer
        Correct Answer:- Option-B
Question12:-Who is in control of a section?
        A:-Executive Engineer
        B:-Chief Engineer
        C:-Asst Exe Engineer
        D:-Assistant Engineer
        Correct Answer:- Option-D
Question13:-Generally who is responsible for taking and recording measurements?
        A:-Contractor
        B:-Asst Executive Engineer
        C:-Executive Engineer
        D:-Assistant Engineer
        Correct Answer:- Option-D
Question14:-Who is to prepare detailed drawings on field data as per approved designs?
        A:-Assistant Engineer
        B:-3rd Grade Overseer
        C:-Executive Engineer
        D:-Chief Engineer (Designs)
        Correct Answer:- Option-B
Question15:-Who monitor's that contractor faithfully observes Gen. Conditions of contract?
        A:-Assistant Engineer
        B:-Assistant Executive Engineer
        C:-Contractor
        D:-3rd Grade Overseer
        Correct Answer:- Option-D
Question16:-Who is responsible for conducting soil investigation works?
        A:-Lab Technician
        B:-3rd Grade Overseer
        C:-Asst Engineer
        D:-Design Engineer
        Correct Answer:- Option-B
Question17:-What is the duty of a 1st/2nd Grade Draughtsman?
        A:-Approve contractor's bills
        B:-Tabulate tenders
        C:-Design of Bridges
        D:-Issuing approval's to sub: offices
        Correct Answer:- Option-B
Question18:-The finance Branch in a PWD office deals with, ____________.
        A:-Transfers and Postings
        B:-Maintaining service books
        C:-Preparation of Agreements
        D:-Preparing monthly accounts
        Correct Answer:- Option-D
Question19:-Who generally assists the Chief Engineer (Administration) in deputing officers for various training programs?
        A:-Executive Engineer (HR)
        B:-Dy Chief Engineer
        C:-Administrative Officer
        D:-Establishment Officer
        Correct Answer:- Option-A
Question20:-Who conducts enquiries regarding allegations against any PWD staff?
        A:-Chief Engineer (Administration)
        B:-Dy. Chief Engineer (Administration)
        C:-Dy. Chief Engineer (Vigilance)
        D:-Chief Technical Examiner
        Correct Answer:- Option-C
Question21:-The Electrical Wing of PWD deals with _____________.
        A:-Asst Engineer Electrical
        B:-Asst Exe Engineer Electrical
        C:-Executive Engineer Electrical
        D:-Suptg. Engineer Electrical
        Correct Answer:-Question Cancelled
Question22:-Who is responsible for the implementation of RMMS?
        A:-Chief Engineer Administration
        B:-Dy. Chief Engineer R & B
        C:-Director Designs
        D:-Executive Engineer (Planning R & B)
        Correct Answer:- Option-D
Question23:-Who is responsible for emergency works under roads section?
        A:-Executive Engineer, Roads
        B:-Chief Engineer, Roads
        C:-Asst Engineer, Roads
        D:-Suptg. Engineer, Roads
        Correct Answer:- Option-C
Question24:-Who manages specialized projects?
        A:-Chief Engineer, Projects
        B:-Chief Engineer, Roads
        C:-Chief Engineer, NH
        D:-Chief Engineer, Administration
        Correct Answer:- Option-A
Question25:-Administrative Officer is under direct control of ___________.
        A:-Chief Engineer, Roads
        B:-Chief Engineer, Administration
        C:-Chief Engineer, Projects
        D:-Chief Engineer, Buildings
        Correct Answer:- Option-B
Question26:-Whose duty is to maintain the departmental vehicle log books?
        A:-Driver
        B:-Assistant Engineer
        C:-Administrative officer
        D:-Mechanical Engineer
        Correct Answer:- Option-A
Question27:-Who assists the EE in exercising financial control over the transactions of the Division?
        A:-Dy. Executive Engineer
        B:-Senior superintendent
        C:-Divisional Accountant
        D:-Head clerk
        Correct Answer:- Option-C
Question28:-Who is in OVERALL control of the HR & Training Cell?
        A:-Executive Engineer
        B:-Chief Engineer, Administration
        C:-Dy. Chief Engineer, Administration
        D:-HR Manager
        Correct Answer:- Option-B
Question29:-The test required to be passed before declaration of probation
        A:-PSC recruitment test
        B:-PWD proficiency test
        C:-KPWD training exam
        D:-Departmental test by KPSC
        Correct Answer:- Option-D
Question30:-What is the duration of Orientation Training for new recruitees?
        A:-2 weeks
        B:-3 to 6 days
        C:-1 week
        D:-2 to 3 days
        Correct Answer:- Option-A
Question31:-Who supervises the IT cell?
        A:-Chief Engineer, Designs
        B:-Chief IT Engineer
        C:-Executive Engineer IT
        D:-Sr Software Engineer
        Correct Answer:- Option-C
Question32:-How many categories of works are included in the budget head of R & B?
        A:-1
        B:-2
        C:-3
        D:-4
        Correct Answer:- Option-D
Question33:-To whom shall original works of NH to be proposed?
        A:-MoRTH
        B:-PWD Secretary
        C:-Office of Prime Minister
        D:-NHAI
        Correct Answer:- Option-A
Question34:-Who receives the money collected as Test FEES by KHRI?
        A:-Kerala Road Fund Board
        B:-PWD
        C:-Finance Department
        D:-Central Road Research Institute
        Correct Answer:- Option-A
Question35:-Which is NOT an external funding agency for PWD works?
        A:-NABARD
        B:-Govt. of India
        C:-World Bank
        D:-Asian Development Bank
        Correct Answer:- Option-B
Question36:-What is GIS?
        A:-Geographical Information System
        B:-Geometrical Information System
        C:-General Information System
        D:-Global Information System
        Correct Answer:- Option-A
Question37:-Who carries out GPS field survey in PWD?
        A:-Central GIS unit
        B:-Local GIS unit
        C:-Circle Office
        D:-Department of surveys
        Correct Answer:- Option-B
Question38:-Who shall proceed to site in receiving an information of Major Accident?
        A:-Chief Engineer
        B:-Executive Engineer
        C:-Suptng. Engineer
        D:-Asst Engineer
        Correct Answer:- Option-D
Question39:-Which cell co-ordinates the Road Safety Activities of PWD?
        A:-HR Cell
        B:-Road Safety cell
        C:-IT cell
        D:-RMMS cell
        Correct Answer:- Option-B
Question40:-How is Road safety Black Spot at which accidents are clustered are identified?
        A:-Jn/bend/short length of 300-500 m
        B:-Location where no lighting
        C:-Location where the road is black
        D:-Location painted with black spots
        Correct Answer:- Option-A
Question41:-What is the IRC code for Road signs?
        A:-IRC 67-2001
        B:-IRC 28-2006
        C:-IRC 78-2014
        D:-IRC 112-2011
        Correct Answer:- Option-A
Question42:-Specification for Road safety works are available in ____________.
        A:-PWD Manual
        B:-PWD Code
        C:-PRICE software
        D:-MoRTH specification for Road and Bridges
        Correct Answer:- Option-D
Question43:-What is the frequency of inspection by AE buildings for certification of safety?
        A:-Once a year
        B:-Every 3 months
        C:-Every six months
        D:-Twice a year
        Correct Answer:- Option-D
Question44:-Who has the responsibility of Bridge Safety?
        A:-Chief Engineer
        B:-Assistant Engineer
        C:-Asst Exe Engineer
        D:-Executive Engineer
        Correct Answer:- Option-D
Question45:-Who shall arrange Refugee Camps in Disaster in liaison with district collector?
        A:-Chief Engineer
        B:-Assistant Engineer
        C:-Asst Exe Engineer
        D:-Executive Engineer
        Correct Answer:- Option-D
Question46:-What kind of pollution occurs due to gas, dust, fumes and odour?
        A:-Water pollution
        B:-Noise pollutions
        C:-Air pollution
        D:-Land pollutions
        Correct Answer:- Option-C
Question47:-What is act to be followed for environmental aspects?
        A:-National and State Acts of India``
        B:-World Bank Acts
        C:-International Environmental Act
        D:-UN Environmental Act
        Correct Answer:- Option-A
Question48:-Who is to issue labour Licence for construction?
        A:-Department of Explosives
        B:-Department of Labour
        C:-Department of Environment
        D:-PWD
        Correct Answer:- Option-B
Question49:-What happens when contractor fails to comply standard EMP?
        A:-He is black listed
        B:-Work cancelled at risk and cost
        C:-He is sent for compulsory training
        D:-Receives only partial payment
        Correct Answer:- Option-D
Question50:-What is the study conducted for social impact of a project?
        A:-Env. Impact Assessment
        B:-Social Impact Assessment
        C:-Construction Impact Assessment
        D:-Project Impact Assessment
        Correct Answer:- Option-B
Question51:-Investigations to be carried out in how many phases
        A:-2
        B:-3
        C:-4
        D:-5
        Correct Answer:- Option-A
Question52:-Who is responsible to conduct preliminary investigation?
        A:-Asst Engineer
        B:-Asst Exe Engineer
        C:-Executive Engineer
        D:-Suptg Engineer
        Correct Answer:- Option-A
Question53:-What is meant by MSL?
        A:-Median Safe Level
        B:-Most Suitable Level
        C:-Mean Sea Level
        D:-Minimum Survey Level
        Correct Answer:- Option-C
Question54:-Which reference book shall be used for investigation of Road Works?
        A:-IRC 58-2002
        B:-IRC 37-2001
        C:-IRC : SP : 19-2001
        D:-IRC 67-2001
        Correct Answer:- Option-C
Question55:-Axle Load studies are done in ____________.
        A:-Soil investigation
        B:-Building investigation
        C:-Bridge investigation
        D:-Road Investigation
        Correct Answer:- Option-D
Question56:-Selection of materials for road construction shall be strictly as per ___________.
        A:-Local conditions
        B:-Standard Data Book
        C:-Old Approved Estimates
        D:-IRC/MoRTH guide lines
        Correct Answer:- Option-D
Question57:-What is the order of construction of shoulder and pavement?
        A:-Shoulder and then pavement each layer by layer
        B:-Pavement and then shoulder each layer by layer
        C:-Full pavement thickness and then full shoulder thickness
        D:-Full shoulder thickness and then full pavement thickness
        Correct Answer:- Option-B
Question58:-Which document provides the Qualification Criteria for Bids?
        A:-PWD Manual
        B:-PWD code
        C:-Bid document
        D:-Contractor's Manual
        Correct Answer:- Option-C
Question59:-What is NOT a factors in controlling Road Alignment?
        A:-Traffic
        B:-Geometric design
        C:-Economy
        D:-Axle Load
        Correct Answer:- Option-D
Question60:-How many stages are there for Engineering Surveys for Roads?
        A:-2
        B:-4
        C:-6
        D:-8
        Correct Answer:- Option-B
Question61:-What is required for determination of Road Vertical Profile?
        A:-Land Availability
        B:-Financial Sanction
        C:-Design of Vertical Curves
        D:-Design of structures
        Correct Answer:- Option-C
Question62:-What is NOT a factor in selecting site for Bridge?
        A:-Scenery
        B:-High and Stable Banks
        C:-Width of channel
        D:-Depth of channel
        Correct Answer:- Option-A
Question63:-What is the length of straight stretches of river required U/S and D/S of bridge site?
        A:-500 m
        B:-300 m
        C:-200 m
        D:-100 m
        Correct Answer:- Option-D
Question64:-What is the objective of sub surface investigation for Bridges?
        A:-Determine the depth of water
        B:-Determine the width of River
        C:-Determine the Chemistry of water
        D:-Determine suitability of soil/rock
        Correct Answer:- Option-D
Question65:-IS : 4453-1980 shall be referred for _____________.
        A:-Super structure design of building
        B:-Site Exploration
        C:-Foundation design of building
        D:-Elevation design of building
        Correct Answer:- Option-B
Question66:-How many types of estimates are there in PWD?
        A:-4
        B:-5
        C:-3
        D:-6
        Correct Answer:- Option-D
Question67:-How many parts are there for a detailed estimate?
        A:-5
        B:-6
        C:-8
        D:-7
        Correct Answer:- Option-D
Question68:-What is the role of State PWD regarding National Highways?
        A:-Sourcing funds
        B:-Issuing NH numbers
        C:-Agent for Govt. of India
        D:-Owner for State Govt.
        Correct Answer:- Option-C
Question69:-Who accords AS for works on Raj Bhavan?
        A:-Controller, Governor's Household
        B:-Comptroller and Auditor General
        C:-Accountant General
        D:-Secretary, Finance
        Correct Answer:- Option-A
Question70:-What is the percentage charges for plan and estimate for private deposit works?
        A:-2%
        B:-3%
        C:-2.5%
        D:-5%
        Correct Answer:- Option-C
Question71:-What is the rates for works to be followed by all Govt. Departments?
        A:-Market Rates
        B:-CPWD Rates
        C:-Kerala PWD Schedule of Rates
        D:-Own rates for each department
        Correct Answer:- Option-C
Question72:-What is the Data to be followed for preparing estimates for roads?
        A:-Kerala PWD data
        B:-MoRTH data
        C:-Self made data
        D:-Statistic Dept. Data
        Correct Answer:- Option-B
Question73:-Who shall fix the Local Market Rate?
        A:-Chief Engineer
        B:-Executive Engineer, Buildings
        C:-Executive Engineer, Roads
        D:-Executive Engineer, Designs
        Correct Answer:- Option-B
Question74:-Who accords administrative sanction?
        A:-Chief Engineer Administration
        B:-Administrative Officer, PWD
        C:-Executive Engineer
        D:-Government
        Correct Answer:- Option-D
Question75:-What is the third type of sanction required other than AS & TS for works?
        A:-Financial Sanction
        B:-Commencement Sanction
        C:-Feasibility Sanction
        D:-Viability Sanction
        Correct Answer:- Option-A
Question76:-Who is the Highest Registering Authority for contractors?
        A:-Chief Engineer
        B:-Suptg. Engineer
        C:-Executive Engineer
        D:-Government
        Correct Answer:- Option-B
Question77:-What is the limit of Electrical works that can be taken up by A category contractors?
        A:-All works
        B:-Up to 55 lakhs
        C:-Up to 6 lakhs
        D:-Up to 15 lakhs
        Correct Answer:- Option-A
Question78:-When is Departmental Execution method adopted?
        A:-At the discretion of CE
        B:-When there is no contractor
        C:-When the work complicated technically
        D:-For convenience
        Correct Answer:- Option-B
Question79:-In which contract type the rates are quoted as percentage above or below
        A:-Item rate contract
        B:-Piece work contract
        C:-Lump sum contract
        D:-Percentage rate contract
        Correct Answer:- Option-D
Question80:-How much minimum land shall be available for Road Construction?
        A:-60%
        B:-100%
        C:-50%
        D:-25%
        Correct Answer:- Option-A
Question81:-When is Pre qualification bidding procedure followed
        A:-Works costing more than 5 crore
        B:-Works costing more than 10 crore
        C:-Works costing more than 15 crore
        D:-Works costing more than 50 crore
        Correct Answer:- Option-A
Question82:-At what level shall Pre bid meeting to be held for Large works
        A:-Chief Engineer's level
        B:-Govt. level
        C:-Suptg. Engineer's level
        D:-Executive Engineer's level
        Correct Answer:- Option-A
Question83:-When can negotiations made for tenders?
        A:-No negotiations after opening
        B:-When the amount is too high
        C:-When the amount is too low
        D:-When the registration is not valid
        Correct Answer:- Option-A
Question84:-Who has to prepare the Working Drawings?
        A:-Asst Engineer
        B:-Asst Executive Engineer
        C:-Design wing
        D:-Contractor's site Engineer
        Correct Answer:- Option-D
Question85:-What is the maximum limit of payment without detailed scrutiny of bills?
        A:-90%
        B:-50%
        C:-60%
        D:-75%
        Correct Answer:- Option-D
Question86:-Agreed rate is applicable up to what % of excess of that particular item
        A:-10%
        B:-15%
        C:-25%
        D:-50%
        Correct Answer:- Option-C
Question87:-Where shall the drawing be maintained?
        A:-Division office
        B:-Site office
        C:-Section office
        D:-Sub division office
        Correct Answer:- Option-B
Question88:-What is the remedy for over excavation?
        A:-Fill it back with earth
        B:-No payment for excess earth work
        C:-Fill up by concrete/Masonry
        D:-Charge FINE on contractor
        Correct Answer:- Option-C
Question89:-What is the minimum time allowed to drain after aggregates are washed for Road Works?
        A:-24 Hrs
        B:-48 Hrs
        C:-72 Hrs
        D:-12 Hrs
        Correct Answer:- Option-C
Question90:-Normally, how many hours required for removal of shuttering of beam faces?
        A:-24 Hrs
        B:-48 Hrs
        C:-72 Hrs
        D:-7 days
        Correct Answer:- Option-A
Question91:-What item above 1000 cu.m shall be reported to Chief Technical Examiner?
        A:-Aggregates for road works
        B:-Concrete
        C:-Earth work
        D:-Masonry
        Correct Answer:- Option-C
Question92:-Who normally prepares estimate for electrical works?
        A:-AE KSEB
        B:-AE electrical, PWD
        C:-Any approved electrician
        D:-Electrical consultants
        Correct Answer:- Option-B
Question93:-Type of wiring shall be resorted to as far as possible in electrification works
        A:-concealed wiring
        B:-open wiring
        C:-piped wiring
        D:-underground wiring
        Correct Answer:- Option-B
Question94:-What is the threshold for technical audit?
        A:-All maintenance works
        B:-All original works above 5 crores
        C:-All maintenance works above 5 crores
        D:-All original works
        Correct Answer:- Option-B
Question95:-Cationic Bitumen Emulsion is advantageous for ___________ road works.
        A:-Both New and Maintenance
        B:-Only maintenance works
        C:-Only new works
        D:-Only for BM & BC works
        Correct Answer:- Option-A
Question96:-What is the renewal frequency of BM & AC roads?
        A:-3 years
        B:-5 years
        C:-10 years
        D:-7 years
        Correct Answer:- Option-D
Question97:-Where is the register of buildings kept?
        A:-Section
        B:-Sub Division
        C:-Division
        D:-Circle
        Correct Answer:- Option-C
Question98:-What is the periodicity of varnishing and oiling work of govt. buildings?
        A:-Once in a year
        B:-Twice in year
        C:-Once in two years
        D:-Once in five years
        Correct Answer:- Option-C
Question99:-Who acts as the estate officer of all Govt. Buildings?
        A:-Chief Engineer Buildings
        B:-District collector
        C:-Asst Engineer Buildings
        D:-Executive Engineer Buildings
        Correct Answer:- Option-D
Question100:-What is the basic value on which depreciation is applied during building evaluation?
        A:-Market value
        B:-Estimated capital value
        C:-Value shown in registration
        D:-Value on which tax is paid
        Correct Answer:- Option-B