Departmental Test for the Executive Staff of KSEBL - Electricity Supply Act – III Paper


Electricity Supply Act - III PAPER
Date of Examination :25-09-2019


Question1:-A power plant set up by any association of persons for generating electricity primarily for use of members of such association is known
as
        A:-Independent generating plant
        B:-Captive generating plant
        C:-Small generating plant
        D:-Distributed generating plant
        Correct Answer:- Option-B
Question2:-A process that simultaneously produces two or more forms of useful energy including electricity is called
        A:-Cogeneration
        B:-Renewable generation
        C:-Self-generation
        D:-Hybrid generation
        Correct Answer:- Option-A
Question3:-The high voltage backbone system of inter-connected transmission lines, sub-stations and generating plants
        A:-Transmission system
        B:-Dedicated transmission lines
        C:-Grid
        D:-Power system
        Correct Answer:- Option-C
Question4:-The electricity system set-up to generate power and distribute electricity in a specified area without connection to the grid is called
        A:-Independent system
        B:-Substation
        C:-Distribution system
        D:-Stand alone system
        Correct Answer:- Option-D
Question5:-Grid standards means the standards specified by the
        A:-CERC
        B:-CEA
        C:-APTEL
        D:-CTU
        Correct Answer:- Option-B
Question6:-The National electricity policy is prepared by
        A:-Central government
        B:-Central electricity regulatory commission
        C:-Central electricity authority
        D:-Appellate tribunal
        Correct Answer:- Option-A
Question7:-Every person, who has constructed a captive generating plant and maintains and operates such plant, shall have the right to
        A:-Open access
        B:-Trading
        C:-Franchising
        D:-Distribution
        Correct Answer:- Option-A
Question8:-License is not required for
        A:-Transmission of electricity
        B:-Distribution of electricity
        C:-Generation of electricity
        D:-Trading of electricity
        Correct Answer:- Option-C
Question9:-The central transmission utility within _________ after the receipt of the copy of the application for license shall sent its
recommendations to the central commission
        A:-7 days
        B:-15 days
        C:-30 days
        D:-45 days
        Correct Answer:- Option-C
Question10:-Unless revoked, a licence shall continue to be in force for a period of
        A:-5 years
        B:-10 years
        C:-20 years
        D:-25 years
        Correct Answer:- Option-D
Question11:-Which of the following is not a reason to suspend the license of a distribution licensee?
        A:-Persistently failed to maintain uninterrupted supply
        B:-Unable to discharge the functions imposed on it
        C:-Broken the terms and conditions of licence
        D:-Fail to comply the direction of government
        Correct Answer:- Option-D
Question12:-The NLDC is constituted for optimum scheduling and despatch of electricity among
        A:-RLDCs
        B:-SLDCs
        C:-CTUs
        D:-STUs
        Correct Answer:- Option-A
Question13:-The SLDC can be operated by
        A:-A state Government company
        B:-An authority constituted by any central Act
        C:-A corporation established by central Government
        D:-None of the above
        Correct Answer:- Option-A
Question14:-This of the following is not a function of the central transmission utility
        A:-Planning and co-ordination relating to inter-state transmission system with state transmission utilities
        B:-Planning and co-ordination relating to inter-state transmission system with state generating companies
        C:-Planning and co-ordination relating to intra-state transmission system with authority
        D:-Undertake transmission of electricity through inter-state transmission system
        Correct Answer:- Option-C
Question15:-If any generating company fails to comply with the directions issued by SLDC, it is liable to pay a penalty not exceeding
        A:-Rs. 15 lacs
        B:-Rs. 20 lacs
        C:-Rs. 5 lacs
        D:-Rs. 10 lacs
        Correct Answer:- Option-C
Question16:-Any consumer aggrieved by the order of CGRF can approach
        A:-Ombudsman
        B:-High court
        C:-State regulatory commission
        D:-Distribution licensee
        Correct Answer:- Option-A
Question17:-The standards of performance of a licensee shall be specified by
        A:-Appropriate Government
        B:-Central electricity authority
        C:-Appropriate commission
        D:-Licensee
        Correct Answer:- Option-C
Question18:-No person other than a licensee shall transmit electricity in any street at a rate exceeding
        A:-200 W and 110 V
        B:-220 W and 90 V
        C:-230 W and 120 V
        D:-250 W and 100 V
        Correct Answer:- Option-D
Question19:-No tariff or part of any tariff may ordinarily be amended more frequently than
        A:-Once in any financial year
        B:-Twice in any financial year
        C:-Once in five years
        D:-Once in three years
        Correct Answer:- Option-A
Question20:-The regulatory commission shall accept/reject a tariff petition within _________ from the date of receipt of the application
        A:-120 days
        B:-90 days
        C:-60 days
        D:-30 days
        Correct Answer:- Option-A
Question21:-Provisions of Act with the prior approval of
        A:-Appropriate commission
        B:-Appropriate government
        C:-Central electricity authority
        D:-Ombudsman
        Correct Answer:- Option-B
Question22:-The central electricity authority shall consist of not more than __________ full-time members
        A:-Fourteen
        B:-Fifteen
        C:-Eight
        D:-Twelve
        Correct Answer:- Option-C
Question23:-Which of the following is not a function of CEA?
        A:-Specify safety requirements
        B:-Specify the technical standards
        C:-Specify the conditions of meter installations
        D:-Specify Grid code
        Correct Answer:- Option-D
Question24:-The central commission shall consist of
        A:-Chairperson and two other members
        B:-Chairperson and three other members
        C:-Chairperson and four other members
        D:-Chairperson and five other members
        Correct Answer:- Option-B
Question25:-The selection committee shall finalise the selection of the member of central commission within ___________ on which the reference is
made to it
        A:-1 months
        B:-2 months
        C:-3 months
        D:-4 months
        Correct Answer:- Option-C
Question26:-Which of the following is not a function of central commission?
        A:-Regulate the tariff of central generating companies
        B:-Regulate the inter-state transmission of electricity
        C:-Adjudicate disputes
        D:-Advice central Government
        Correct Answer:- Option-D
Question27:-The selection committee to select a member of SERC shall recommend a panel of
        A:-1 name
        B:-2 names
        C:-3 names
        D:-4 names
        Correct Answer:- Option-B
Question28:-The chairperson or member of SERC shall not hold office after he has attained the age of
        A:-60 years
        B:-65 years
        C:-68 years
        D:-70 years
        Correct Answer:- Option-B
Question29:-This is a reason to remove a member from the commission
        A:-Adjudged an insolvent
        B:-Convicted of an offence involving moral turpitude
        C:-Guilty of proved misbehaviour
        D:-All the above
        Correct Answer:- Option-D
Question30:-The state electricity regulatory commission fund shall not be used for meeting
        A:-Salary of chairperson and members of the state commission
        B:-Expenses of the state commission
        C:-Expenses for purposes authorised by the Act
        D:-Expenses of the central commission
        Correct Answer:- Option-D
Question31:-The central government issue direction to central commission in matters of policy as per
        A:-Section 107
        B:-Section 108
        C:-Section 109
        D:-Section 110
        Correct Answer:- Option-A
Question32:-Any person aggrieved by the order made by a state Commission can file appeal before
        A:-Central electricity authority
        B:-Central electricity regulatory commission
        C:-Appellate tribunal for electricity
        D:-Civil court
        Correct Answer:- Option-C
Question33:-This of the following does not come under the purview of unauthorised use of electricity
        A:-By any artificial means
        B:-Through a tampered meter
        C:-Purpose other than for which the usage of electricity was authorised
        D:-Without changing the ownership of connection
        Correct Answer:- Option-D
Question34:-To file an appeal against an order of assessment under section 126, the appellant shall deposit an amount equal to
        A:-Full assessed amount
        B:-Half of the assessed amount
        C:-One third of the assessed amount
        D:-One fourth of the assessed amount
        Correct Answer:- Option-B
Question35:-The transfer value of any assets transferred shall be determined based on the
        A:-Revenue potential
        B:-Market value
        C:-Fair value
        D:-Book value
        Correct Answer:- Option-A
Question36:-The fine for theft of electricity for the first conviction, where the load abstracted does not exceed 10 kW, is
        A:-6 times the financial gain
        B:-4 times the financial gain
        C:-3 times the financial gain
        D:-5 times the financial gain
        Correct Answer:- Option-C
Question37:-Whoever, negligently breaks, injures, throws down or damages any material connected with the supply of electricity, shall be
punishable with fine which may extend to
        A:-Rs. 20,000
        B:-Rs. 10,000
        C:-Rs. 5,000
        D:-Rs. 1,000
        Correct Answer:- Option-B
Question38:-Compounding rate for Agricultural consumer is
        A:-Rs. 20,000 per kW
        B:-Rs. 10,000 per kW
        C:-Rs. 2,000 per kW
        D:-Rs. 4,000 per kW
        Correct Answer:- Option-C
Question39:-In the case of any conviction in a summary trial, it shall be lawful for a special court to pass a sentence of imprisonment for a term
        A:-Not exceeding 5 years
        B:-Not exceeding 4 years
        C:-Not exceeding 3 years
        D:-Not exceeding 2 years
        Correct Answer:- Option-A
Question40:-The appropriate government may, be notification, appoint duly qualified persons to be chief electrical inspector or electrical
inspectors as per
        A:-Section 161
        B:-Section 162
        C:-Section 163
        D:-Section 164
        Correct Answer:- Option-B
Question41:-The chairperson of the forum of regulators shall be the
        A:-Chairperson of the central Electricity authority
        B:-Chairperson of the appellate tribunal for electricity
        C:-Chairperson of the central commission
        D:-Chairperson of a state commission
        Correct Answer:- Option-C
Question42:-Any rule or regulation made under the Act can have effect even if it is inconsistent with any other provisions of the
        A:-Consumer protection Act, 1986
        B:-Atomic energy Act, 1962
        C:-Railway Act 1989
        D:-Indian Electricity Act, 1910
        Correct Answer:- Option-D
Question43:-An officer designated by the Government of Kerala under the provisions of section 126 of the Act
        A:-Assessing officer
        B:-Authorised officer
        C:-Electrical inspector
        D:-Inspecting officer
        Correct Answer:- Option-A
Question44:-The connected load installed by the consumer at the time of executing the service connection agreement and recorded in kW/kVA in
the schedule to the agreement is the
        A:-Connected load
        B:-Contract demand
        C:-Contracted connected load
        D:-Contracted load
        Correct Answer:- Option-C
Question45:-This of the following is not a power intensive unit
        A:-HT induction arc furnace
        B:-EHT calcium carbide manufacturing
        C:-HT electro chemical processes
        D:-EHT heating load not exceeding 20% of its total connected load
        Correct Answer:- Option-D
Question46:-Supply of electricity given for a specified period is called
        A:-Temporary supply
        B:-Temporary extension
        C:-Protected supply
        D:-Short term supply
        Correct Answer:- Option-A
Question47:-Extra high tension means a voltage of and above __________ under normal conditions
        A:-11000 Volts
        B:-22000 Volts
        C:-33000 Volts
        D:-66000 Volts
        Correct Answer:- Option-D
Question48:-The permissible limit of voltage variation at the point of supply in case of LT is
        A:-6 percent on lower side
        B:-9 percent on lower side
        C:-9 percent on higher side
        D:-10 percent on higher side
        Correct Answer:- Option-A
Question49:-The maximum connected load permissible for LT three phase shall be limited to
        A:-150 kVA
        B:-100 kVA
        C:-75 kVA
        D:-50 kVA
        Correct Answer:- Option-B
Question50:-Consumers shall install a suitable device for earth leakage protection
        A:-If connected load is above 4 kW
        B:-If connected load is above 5 kW
        C:-If connected load is above 10 kW
        D:-Irrespective of the connected load
        Correct Answer:- Option-D
Question51:-It shall be obligatory for all consumers to restrict the harmonics dumped by them to the levels stipulated by the
        A:-IEEE standard
        B:-IEE standard
        C:-IEC standard
        D:-Indian standard
        Correct Answer:- Option-A
Question52:-If the licensee imposes load shedding in exigencies based on the directions issued by the SLDC, the licensee shall submit a report to
commission within
        A:-Two days
        B:-Three days
        C:-Five days
        D:-Seven days
        Correct Answer:- Option-B
Question53:-The expenditure for extension of the distribution system for giving new service connection need not be borne by the respective
applicant in case of
        A:-Contract demand of 1 MW
        B:-High rise building
        C:-Power intensive units
        D:-Connection with dedicated feeder
        Correct Answer:- Option-A
Question54:-This of the following is not accepted as the proof of identify of an individual
        A:-Driving licence
        B:-Ration card
        C:-PAN card
        D:-Ownership certificate
        Correct Answer:- Option-D
Question55:-The norm for estimating the connected load of a domestic building is
        A:-600 watts/10 square metre
        B:-500 watts/10 square metre
        C:-400 watts/10 square metre
        D:-300 watts/10 square metre
        Correct Answer:- Option-B
Question56:-If the installation of an LT consumer is not ready to receive the supply even after the work of the licensee is completed, then the
licensee shall serve a notice directing him to take supply within
        A:-30 days
        B:-45 days
        C:-60 days
        D:-90 days
        Correct Answer:- Option-C
Question57:-A domestic consumer belonging to BPL category shall not be required to provide security deposits so long as his monthly
consumption does not exceed
        A:-Twenty units
        B:-Thirty units
        C:-Forty units
        D:-None of the above
        Correct Answer:- Option-B
Question58:-The date of inspection shall be scheduled within __________ five working days from the date of receipt of application form
        A:-Three working days
        B:-Five working days
        C:-Seven working days
        D:-Ten working days
        Correct Answer:-Question Cancelled
Question59:-For HT service connections, the licensee shall issue demand note to the applicant within _________ on receipt of application form
        A:-Seven days
        B:-Ten days
        C:-Fourteen days
        D:-Thirty days
        Correct Answer:- Option-D
Question60:-The time limit prescribed for providing LT connection where extension of line is not required is
        A:-Ten days
        B:-Fourteen days
        C:-Thirty days
        D:-Forty five days
        Correct Answer:- Option-C
Question61:-Temporary connection shall not ordinarily be granted for a period exceeding
        A:-One month
        B:-Three months
        C:-Six months
        D:-One year
        Correct Answer:- Option-D
Question62:-Once the consumer made the remittance, the time limit prescribed for conversion from single phase to three phases is
        A:-Thirty days
        B:-Forty-five days
        C:-Sixty days
        D:-Ninety days
        Correct Answer:- Option-B
Question63:-The time limit prescribed for completing the shifting of transformer from the date of payment of expenditure
        A:-Fifteen days
        B:-Thirty days
        C:-Forty days
        D:-Sixty days
        Correct Answer:- Option-B
Question64:-The licensee shall issue a notice to an HT consumer directing him to apply for enhancement of contract demand, if the maximum
demand recorded exceeds the contract demand for
        A:-Two billing cycle
        B:-Three billing cycle
        C:-Four billing cycle
        D:-Five billing cycle
        Correct Answer:- Option-B
Question65:-While estimating the total load of a consumer, the loads of the following equipment and apparatus shall be considered
        A:-Firefighting equipment
        B:-Uninterrupted power supply equipment
        C:-Switch mode power supply system
        D:-Stand by equipment without change over switch
        Correct Answer:- Option-D
Question66:-Who of the following is not a member of Electricity Supply Code Review Panel (ESCRP)
        A:-Chief electrical inspector
        B:-Chief executive of the state transmission utility
        C:-Trade union representative
        D:-Small scale industrial consumer's representative
        Correct Answer:- Option-C
Question67:-HVDC means DC voltage above ______________ used for transmission of power
        A:-100000 Volts
        B:-90000 Volts
        C:-76500 volts
        D:-66000 volts
        Correct Answer:- Option-A
Question68:-Linked switch means a switch with all the poles mechanically linked to operate
        A:-Intermittently
        B:-Frequently
        C:-Alternately
        D:-Simultaneously
        Correct Answer:- Option-D
Question69:-The electrical safety officer shall be an electrical engineering degree holder with at least ____________ of experience in operation and
maintenance of electrical installations
        A:-Ten years
        B:-Seven years
        C:-Five years
        D:-Three years
        Correct Answer:- Option-C
Question70:-The owner of every installation shall affix a danger notice permanently in a conspicuous position if the voltage
        A:-Exceeds 100 V
        B:-Exceeds 150 V
        C:-Exceeds 200 V
        D:-Exceeds 250 V
        Correct Answer:- Option-D
Question71:-Every electrical installation already connected to the supply system of a licensee shall be periodically inspected and tested by an
authority directed by the state government at intervals not exceeding
        A:-Six years
        B:-Three years
        C:-Ten years
        D:-Five years
        Correct Answer:- Option-B
Question72:-On application of 500 V DC between each live conductor and earth for a period of one minute, the insulation resistance of installation
and equipment of voltage not exceeding 650 V shall be at least
        A:-1 Mega Ohm
        B:-2 Mega Ohm
        C:-4 Mega Ohm
        D:-5 Mega Ohm
        Correct Answer:- Option-A
Question73:-Protection against earth fault or leakage shall be required for all generators with rating
        A:-25 kVA and above
        B:-50 kVA and above
        C:-75 kVA and above
        D:-100 kVA and above
        Correct Answer:- Option-D
Question74:-The minimum factor of safety for stay-wires, guard-wires or bearer-wires based on the ultimate tensile strength of the wire shall be
        A:-2.0
        B:-3.0
        C:-3.5
        D:-2.5
        Correct Answer:- Option-D
Question75:-No conductor of an overhead line of voltage not exceeding 650 V erected across any street shall at any part there of be at a height
less than
        A:-5.8 metres
        B:-6.1 metres
        C:-5.5 metres
        D:-6.0 metres
        Correct Answer:- Option-A
Question76:-When a 33 kV overhead line passes above or adjacent to any building or part of a building, the vertical clearance above the highest
part of the building immediately under such line shall not less than
        A:-2.5 metres
        B:-3.7 meters
        C:-2.0 metres
        D:-3.0 metres
        Correct Answer:- Option-B
Question77:-Where 110 kV and 220 kV overhead lines cross each other, the minimum clearances between lines shall be
        A:-3.05 metres
        B:-4.58 metres
        C:-5.49 metres
        D:-7.94 metres
        Correct Answer:- Option-B
Question78:-Electricity shall not be transmitted into a mine at a voltage exceeding
        A:-11000 volts
        B:-6600 volts
        C:-3300 volts
        D:-2200 volts
        Correct Answer:- Option-A
Question79:-If the capacitor of a consumer is faulty, KSEBL shall issue notice to the consumer directing him to replace the faulty or unserviceable
capacitor within
        A:-Fifteen days
        B:-One month
        C:-Two months
        D:-Forty five days
        Correct Answer:- Option-B
Question80:-Consumers other than those in LT-IV industry and LT-V agriculture category who install specified capacitors shall be eligible for a
rebate at the rate of
        A:-10 percent on fixed charges
        B:-6 percent on energy charges
        C:-5 percent on energy charges
        D:-5 percent on fixed charges
        Correct Answer:- Option-C
Question81:-ToD tariff shall be applicable to LT-IV industrial consumers having connected load above
        A:-5 kW
        B:-10 kW
        C:-20 kW
        D:-25 kW
        Correct Answer:- Option-C
Question82:-Low voltage surcharge for LT-IV(A) consumers having connected load/contract demand above 100 kW/kVA and availing supply at LT
level
        A:-Rs. 150/kVA/month
        B:-Rs. 175/kVA/month
        C:-Rs. 248/kVA/month
        D:-Rs. 268/kVA/month
        Correct Answer:- Option-A
Question83:-The minimum electricity charges payable during the period of disconnection for a single phase domestic consumer is
        A:-Rs. 20/ month
        B:-Rs. 30/month
        C:-Rs. 50/month
        D:-Rs. 80/month
        Correct Answer:- Option-B
Question84:-The energy charge applicable to LT. V(B) category is
        A:-Rs. 1.50/kWh
        B:-Rs. 2.00/kWh
        C:-Rs. 2.50/kWh
        D:-Rs. 2.90/kWh
        Correct Answer:- Option-C
Question85:-LT VI GENERAL (F) tariff is not applicable to
        A:-Computer training institutes
        B:-Cinema studios
        C:-Insurance companies
        D:-Press clubs
        Correct Answer:- Option-D
Question86:-In campuses where lines and lights are provided by the beneficiary, the energy charge for LT metered supply
        A:-3.90 Rs /kWh
        B:-4.50 Rs /kWh
        C:-4.90 Rs /kWh
        D:-5.70 Rs /kWh
        Correct Answer:- Option-A
Question87:-For conversion from kVA to kW or vice versa, the average power factor is taken as
        A:-0.80
        B:-0.85
        C:-0.90
        D:-0.95
        Correct Answer:- Option-C
Question88:-When colony supply is availed from the HT supply of the consumer, such supply shall be segregated and metered by means of a
sub-meter and the consumption will be charged at
        A:-10 paise extra per kWh
        B:-20 paise extra per kWh
        C:-30 paise extra per kWh
        D:-40 paise extra per kWh
        Correct Answer:- Option-B
Question89:-The monthly demand charge applicable to EHT-General-B category is
        A:-Rs. 260 / kVA
        B:-Rs. 290 / kVA
        C:-Rs. 300 / kVA
        D:-Rs. 370 / kVA
        Correct Answer:- Option-D
Question90:-The power factor incentive applicable to HT and EHT consumers for each 0.01 unit increase in power factor from 0.9 is
        A:-0.20 percent of energy charges
        B:-0.30 percent of energy charges
        C:-0.50 percent of energy charges
        D:-1.00 percent of energy charges
        Correct Answer:- Option-C
Question91:-SOP-14 is prepared by
        A:-Senior superintendent
        B:-Meter reader
        C:-Senior assistant
        D:-Cashier
        Correct Answer:- Option-C
Question92:-Which of the following is not a function of stores?
        A:-Procurement
        B:-Receiving
        C:-Inspection
        D:-Reporting
        Correct Answer:- Option-A
Question93:-A document for recording receipt and inspection of materials received from suppliers
        A:-FRN
        B:-GRN
        C:-MRCI
        D:-MASA
        Correct Answer:- Option-B
Question94:-Numerical ledger does not give information regarding
        A:-Material code
        B:-Material description
        C:-Date of receipt
        D:-Standard rate
        Correct Answer:- Option-D
Question95:-MAT-16 form is
        A:-RIST
        B:-MRCI
        C:-ISTN
        D:-FRN
        Correct Answer:- Option-A
Question96:-This document is the authority for issue of materials from store
        A:-MASA
        B:-MRCI
        C:-PSL
        D:-STN
        Correct Answer:- Option-B
Question97:-The document used for manufacturing operation
        A:-FGRN
        B:-FGTN
        C:-GRN
        D:-ISTN
        Correct Answer:- Option-A
Question98:-This is not an objective of SCM
        A:-Provide uninterrupted flow of materials
        B:-Minimise inventory investment
        C:-Maintain and improve quality
        D:-Avoid unhealthy competition
        Correct Answer:- Option-D
Question99:-This is not a centrally procured item
        A:-Conductor
        B:-Transformer
        C:-LT - CT
        D:-Meter
        Correct Answer:- Option-C
Question100:-This shall be kept along with the materials in store
        A:-Numerical ledger
        B:-Priced stores ledger
        C:-Bin card
        D:-Material issue register
        Correct Answer:- Option-C