07-03-2019 Department Test for the Assistant Electrical Inspectors in the Electrical Inspectorate - I Paper

 FINAL ANSWER KEY 

Paper: Funtions of Electrical Inspectorate ... (Paper I) 

Medium of Question: English 

Date of Examination 07-03-2019 

Question1:-Where is the office of Kerala State Electricity Regulatory Commission located? 

 A:-Thiruvananthapuram 

 B:-Thrissur 

 C:-Ernakulam 

 D:-Kozhikkodu 

 Correct Answer:- Option-A 

Question2:-Which of the following is not a general function of Regional Load Despatch Centre? 

 A:-Exercise Supervision and control over the Interstate transmission system 

 B:-Collect wheeling charges for the energy transmitted 

 C:-Keep accounts of the quantity of electricity transmitted 

 D:-Monitor Grid operations 

 Correct Answer:- Option-B 

Question3:-What is the minimum accuracy class of consumer meters at HT premises? 

 A:-0.5 S 

 B:-0.2 S 

 C:-1 S 

 D:-0.25 S 

 Correct Answer:- Option-A 

Question4:-What is the recommended minimum insulation value (in Mega Ohms) for LV three phase installations? 

 A:-5 

 B:-1 

 C:-3 

 D:-2 

 Correct Answer:- Option-B 

Question5:-What is the distance from a 220 kV tower for which permission from the owner of the tower is required for carrying out cutting of soil?  A:-50 m 

 B:-20 m 

 C:-30 m 

 D:-10 m 

 Correct Answer:- Option-D 

Question6:-How many years experience in practice of Electrical Engineering is required, besides other qualifications, for a person to be appointed as Chief Elect A:-15 

 B:-20 

 C:-10 

 D:-12 

 Correct Answer:- Option-B 

Question7:-When a 400 kV DC line crosses another 400 kV DC line, what is the minimum clearance to be maintained? 

 A:-6.79 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-3.05 m 

 Correct Answer:- Option-C 

Question8:-What is the spacing between an underground EHT cable and a Telecommunication cable? 

 A:-75 cm 

 B:-80 cm 

 C:-50 cm 

 D:-60 cm 

 Correct Answer:- Option-D 

Question9:-Which Regulation of CEA (Measures relating to Electric Supply and Safety) Regulations, 2010 makes it mandatory for owners of overhead lines to pr A:-76 

 B:-81 

 C:-74 

 D:-114 

 Correct Answer:- Option-C 

Question10:-What is the generally required minimum height of trolley wires of a traction feeder? 

 A:-5.5 m 

 B:-5.2 m 

 C:-6.2 m 

 D:-6.5 m 

 Correct Answer:- Option-B 

Question11:-What is the cumulative solar power capacity that can normally be connected to the LT side of a distribution transformer, in terms of the transforme A:-50% 

 B:-25% 

 C:-15% 

 D:-30% 

 Correct Answer:- Option-C 

Question12:-When a 66 kV line crosses a 220 kV line, what is the minimum clearance to be maintained? 

 A:-6.79 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-3.05 m 

 Correct Answer:- Option-B 

Question13:-What is the percentage of ruling tariff applicable for 'Off Peak' usage of energy by an HT consumer? 

 A:-50 

 B:-75 

 C:-100 

 D:-125

 Correct Answer:- Option-B 

Question14:-What is the distance from a substation below which permission from the owner of the substation is required for carrying out blasting of any type?  A:-300 m 

 B:-350 m 

 C:-400 m 

 D:-450 m 

 Correct Answer:- Option-A 

Question15:-How much is the fixed charges for an LT-IV industrial consumer having connected load of 15 KW? 

 A:-Rs.100 

 B:-Rs.80 

 C:-Rs.50 

 D:-Rs.60 

 Correct Answer:- Option-D 

Question16:-What is the minimum vertical clearance specified for a building under a 110 kV line? 

 A:-4.6 m 

 B:-3.7 m 

 C:-2.5 m 

 D:-4.0 m 

 Correct Answer:- Option-A 

Question17:-What is the minimum factor of safety for overhead lines on wooden supports? 

 A:-1.5 

 B:-2.0 

 C:-2.5 

 D:-3.0 

 Correct Answer:- Option-D 

Question18:-What is the minimum horizontal clearance for a building adjacent to an LT line? 

 A:-2.5 m 

 B:-4.6 m 

 C:-1.2 m 

 D:-3.7 m 

 Correct Answer:- Option-C 

Question19:-What is the minimum ground clearance for a 400 kV HVDC line? 

 A:-8.5 m 

 B:-9.4 m 

 C:-10.6 m 

 D:-7.3 m 

 Correct Answer:- Option-B 

Question20:-How many joints are allowed in one span of an overhead line? 

 A:-1 

 B:-4 

 C:-2 

 D:-3 

 Correct Answer:- Option-A 

Question21:-What is the clearance above ground level for an LT overhead line along any street? 

 A:-6.4 m 

 B:-5.8 m 

 C:-6.1 m 

 D:-5.5 m 

 Correct Answer:- Option-D 

Question22:-What is the time limit for restoration of supply in case of break down of overhead lines in Rural Areas? 

 A:-12 hours 

 B:-8 hours 

 C:-16 hours 

 D:-24 hours 

 Correct Answer:- Option-A 

Question23:-What is the frequency of periodical inspection of HT installations in the state? 

 A:-every year 

 B:-once in two years 

 C:-once in three years 

 D:-once in five years 

 Correct Answer:- Option-A 

Question24:-What is the rate of Electricity Duty per unit of consumption applicable to HT consumers in the state? 

 A:-1.2 paise 

 B:-12 paise 

 C:-100 paise 

 D:-10 paise 

 Correct Answer:- Option-D 

Question25:-What should be the minimum height to be provided for a passage behind a panel? 

 A:-1 m 

 B:-1.5 m 

 C:-1.6 m 

 D:-1.8 m 

 Correct Answer:- Option-D 

Question26:-What is the time limit for restoration of supply in case of failure of distribution transformer in difficult areas?  A:-72 hours 

 B:-48 hours 

 C:-16 hours 

 D:-24 hours 

 Correct Answer:- Option-B 

Question27:-What is the prescribed periodicity for testing of consumers' meters? 

 A:-2 years 

 B:-3 years

 C:-4 years 

 D:-5 years 

 Correct Answer:- Option-D 

Question28:-Which is the IS for fire fighting systems in substations? 

 A:-3646/1966 

 B:-3034/1993 

 C:-8061/1976 

 D:-3043/1987 

 Correct Answer:- Option-B 

Question29:-What is the clearance above ground level for an LT overhead line along any street? 

 A:-5.5 m 

 B:-5.8 m 

 C:-6.1 m 

 D:-6.4 m 

 Correct Answer:- Option-A 

Question30:-What is the maximum periodicity of inspection of electrical installations? 

 A:-4 years 

 B:-5 years 

 C:-2 years 

 D:-1 year 

 Correct Answer:- Option-B 

Question31:-What is the clearance above ground level for an HT overhead line along any street? 

 A:-5.8 m 

 B:-5.5 m 

 C:-6.1 m 

 D:-6.4 m 

 Correct Answer:- Option-A 

Question32:-When a 110 kV AC line across crosses a 500 KV DC line, what is the minimum clearance to be maintained?  A:-6.79 m 

 B:-7.54 m 

 C:-6.04 m 

 D:-3.05 m 

 Correct Answer:- Option-A 

Question33:-Who appoints the chairperson of Consumer Grievance Redressal Forum? 

 A:-The State Government 

 B:-State electricity Regulatory Commission 

 C:-The Licensee 

 D:-Public Service Commission 

 Correct Answer:- Option-C 

Question34:-What is the maximum allowable percentage of Neutral Voltage in a distribution system? 

 A:-2 

 B:-3 

 C:-4 

 D:-5 

 Correct Answer:- Option-A 

Question35:-What is the minimum horizontal clearance for a building adjacent to a 110 kV line? 

 A:-2.5 m 

 B:-4.6 m 

 C:-1.2 m 

 D:-2.9 m 

 Correct Answer:- Option-D 

Question36:-Which Regulation of CEA (Measures relating to Safety and Electric supply) Regulations, 2010 prescribes earth guarding for overhead lines?  A:-67 

 B:-73 

 C:-60 

 D:-114 

 Correct Answer:- Option-B 

Question37:-How many years' experience in practice of Electrical Engineering is required, besides other qualifications, for a person to be appointed as Electrical A:-15 

 B:-20 

 C:-10 

 D:-8 

 Correct Answer:- Option-C 

Question38:-When a 66 kV line crosses a 110 kV line, what is the minimum clearance to be maintained? 

 A:-6.79 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-3.05 m 

 Correct Answer:- Option-D 

Question39:-When a 220 kV line crosses a 110 kV line, what is the minimum clearance to be maintained? 

 A:-4.58 m 

 B:-3.05 m 

 C:-5.04 m 

 D:-2.44 m 

 Correct Answer:- Option-A 

Question40:-Which is the 'Normal period' of demand for electricity supply specified for the state? 

 A:-10:00 hours to 17:00 hours 

 B:-08:00 hours to 16:00 hours 

 C:-18:00 hours to 22:00 hours 

 D:-06:00 hours to 18:00 hours 

 Correct Answer:- Option-D 

Question41:-What is the minimum horizontal clearance for a building adjacent to an 11 kV line?

 A:-2.5 m 

 B:-4.6 m 

 C:-3.7 m 

 D:-1.2 m 

 Correct Answer:- Option-D 

Question42:-What is the percentage of ruling tariff applicable for 'Peak period' usage of energy by an HT consumer?  A:-200 

 B:-150 

 C:-100 

 D:-125 

 Correct Answer:- Option-B 

Question43:-Which is the IS for Fire Safety of Buildings? 

 A:-3837/1976 

 B:-1646/1997 

 C:-3854/1997 

 D:-732/1989 

 Correct Answer:- Option-B 

Question44:-How much is the connected load above which Energy Conservation Building Code is to be implemented?  A:-1000 kW 

 B:-100 kW 

 C:-500 kW 

 D:-200 kW 

 Correct Answer:- Option-C 

Question45:-What is the minimum horizontal clearance for a building adjacent to a 33 kV line?  A:-2.5 m 

 B:-4.6 m 

 C:-1.2 m 

 D:-2.0 m 

 Correct Answer:- Option-D 

Question46:-What is the rate of Electricity Duty per unit consumption for Public Lighting in the state?  A:-10 paise 

 B:-12 paise 

 C:-0 paise 

 D:-20 paise 

 Correct Answer:- Option-C 

Question47:-What is the allowable variations in voltage on the higher side of HT supply?  A:-6% 

 B:-8% 

 C:-9% 

 D:-12% 

 Correct Answer:- Option-C 

Question48:-What is the minimum insulation value (in Mega Ohms) prescribed for HT installations?  A:-10 

 B:-100 

 C:-50 

 D:-5 

 Correct Answer:- Option-D 

Question49:-What is the ground clearance for a bare 11 kV line elsewhere other than a street?  A:-4.6 m 

 B:-4.9 m 

 C:-5.1 m 

 D:-6.4 m 

 Correct Answer:- Option-A 

Question50:-Which is the 'Peak hours' demand for electricity supply specified for the state?  A:-10:00 hours to 17:00 hours 

 B:-08:00 hours to 16:00 hours 

 C:-18:00 hours to 22:00 hours 

 D:-06:00 hours to 18:00 hours 

 Correct Answer:- Option-C 

Question51:-When an 11 kV line crosses another 11 kV line, what is the minimum clearance to be maintained?  A:-3.05 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-2.44 m 

 Correct Answer:- Option-D 

Question52:-When a 220 kV AC line crosses a 400 kV DC line, what is the minimum clearance to be maintained?  A:-6.79 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-3.05 m 

 Correct Answer:- Option-C 

Question53:-With whom an appeal is to be filed against an order an electricity Inspector?  A:-Deputy Chief Electrical Inspector 

 B:-Chief Electrical Inspector 

 C:-State Government 

 D:-Central Government 

 Correct Answer:- Option-B 

Question54:-How much is the Demand Charges per kVA demand per month for an HT 1(A) consumer?  A:-Rs.300 

 B:-Rs.500 

 C:-Rs.400 

 D:-Rs.600

 Correct Answer:- Option-A 

Question55:-Which is the IS for Switches for domestic use? 

 A:-732/1989 

 B:-2412/1975 

 C:-3043/1987 

 D:-3854/1997 

 Correct Answer:- Option-D 

Question56:-Who is the competent authority to appoint Electricity Ombudsman of a state? 

 A:-The licensee 

 B:-The High Court 

 C:-The State Electricity Regulatory Commission 

 D:-The Chief Electrical Inspector 

 Correct Answer:- Option-C 

Question57:-What is the rate of duty applicable for each unit of energy generated for self consumption? 

 A:-12 paise 

 B:-1.2 paise 

 C:-2 paise 

 D:-20 paise 

 Correct Answer:- Option-B 

Question58:-When a 110 kV line crosses another 110 kV line, what is the minimum clearance to be maintained?  A:-4.58 m 

 B:-3.05 m 

 C:-6.04 m 

 D:-2.44 m 

 Correct Answer:- Option-A 

Question59:-Who appoints Appellate authority? 

 A:-Chief Electrical Inspector 

 B:-State Government 

 C:-Licensee 

 D:-State Electricity Regulatory Commission 

 Correct Answer:- Option-B 

Question60:-What is the maximum permissible number of 1.5 sq.mm single core cables that may be drawn into 20 mm Rigid non-metallic conduit?  A:-4 

 B:-6 

 C:-8 

 D:-10 

 Correct Answer:- Option-B 

Question61:-What is the minimum factor of safety for stay wires? 

 A:-1.5 

 B:-2.0 

 C:-2.5 

 D:-3.0 

 Correct Answer:- Option-C 

Question62:-What is the minimum cross sectional area of a trolley wire? 

 A:-0.5 sq.mm 

 B:-1.0 sq.mm 

 C:-1.5 sq.mm 

 D:-2.0 sq.mm 

 Correct Answer:- Option-A 

Question63:-What is the minimum vertical clearance for a building under a 220 kV line? 

 A:-2.5 m 

 B:-4.6 m 

 C:-5.5 m 

 D:-2.0 m 

 Correct Answer:- Option-C 

Question64:-Who is the ex-officio Secretary of Kerala State Electricity Licensing Board? 

 A:-The Deputy Chief Electrical Inspector of Chief Electrical Inspectorate 

 B:-The Power Secretary 

 C:-Additional Chief Electrical Inspector 

 D:-The Senior most Electrical Inspector 

 Correct Answer:- Option-A 

Question65:-What is the mandatory clearance to be provided in front of an LT panel? 

 A:-75 cm 

 B:-80 cm 

 C:-90 cm 

 D:-100 cm 

 Correct Answer:- Option-D 

Question66:-What is the minimum vertical clearance specified for a building under an LT line? 

 A:-4.6 m 

 B:-3.7 m 

 C:-2.5 m 

 D:-4.0 m 

 Correct Answer:- Option-C 

Question67:-What is the time limit for restoration of supply in case normal fuse off calls in urban areas? 

 A:-8 hours 

 B:-10 hours 

 C:-6 hours 

 D:-12 hours 

 Correct Answer:- Option-C 

Question68:-What is the minimum vertical clearance specified for a building under an HT line? 

 A:-4.6 m 

 B:-3.7 m

 C:-2.5 m 

 D:-4.0 m 

 Correct Answer:- Option-B 

Question69:-How much is the Diversity Factor for domestic Lighting? 

 A:-1 

 B:-2 

 C:-1.5 

 D:-0.75 

 Correct Answer:- Option-C 

Question70:-Which of the following is not under the administrative control of the Department of Electrical Inspectorate?  A:-Kerala State Electricity Licensing Board 

 B:-Kerala State Electricity Board Ltd. 

 C:-The Meter Testing and Standards Laboratory 

 D:-Kerala State Cinema operators Examination Board 

 Correct Answer:- Option-B 

Question71:-Which of the following 'IS' give recommendations on safety procedures and practices in Electricity work?  A:-5216/1982 

 B:-3034/1993 

 C:-3043/1987 

 D:-7689/1989 

 Correct Answer:- Option-A 

Question72:-What is the minimum vertical clearance specified for a building under a 66 kV line? 

 A:-4.6 m 

 B:-3.7 m 

 C:-2.5 m 

 D:-4.0 m 

 Correct Answer:- Option-D 

Question73:-How many months is the maximum validity normally for a temporary connection? 

 A:-12 

 B:-3 

 C:-9 

 D:-6 

 Correct Answer:- Option-A 

Question74:-What is the maximum height at which the Emergency Switch for disconnecting supply to a Multi-storied building has to be located?  A:-1.5 m 

 B:-1.6 m 

 C:-1.7 m 

 D:-1.8 m 

 Correct Answer:- Option-C 

Question75:-What is the maximum connected load that can be connected to a 415 V supply? 

 A:-50 kVA 

 B:-200 kVA 

 C:-100 kVA 

 D:-5 kVA 

 Correct Answer:- Option-C 

Question76:-What is the estimated load, as per norms, for each 10 square meter of constructed area in a commercial installation?  A:-1000 W 

 B:-1500 W 

 C:-2000 W 

 D:-2500 W 

 Correct Answer:- Option-B 

Question77:-Which section of Electricity Act 2003 contains Provisions relating to Safety and Electricity Supply?  A:-33 

 B:-63 

 C:-83 

 D:-53 

 Correct Answer:- Option-D 

Question78:-Which of the following is not a general function of Central Electricity Regulatory Commission? 

 A:-Build and Operate power generating stations 

 B:-Determine tariff for inter state transmission of electricity 

 C:-Regulate inter state transmission of Electricity 

 D:-Specify Grid code having regard to Grid standards 

 Correct Answer:- Option-A 

Question79:-What is the maximum Contract Demand allowed for a consumer availing 11 kv supply? 

 A:-500 kVA 

 B:-100 kVA 

 C:-1000 kVA 

 D:-3000 kVA 

 Correct Answer:- Option-D 

Question80:-What is the percentage of permissible loading unbalance between phases of a Low voltage three phase consumer?  A:-10 

 B:-12 

 C:-8 

 D:-5 

 Correct Answer:- Option-D 

Question81:-When a 220 kV line crosses another 220 kV line, what is the minimum clearance to be maintained?  A:-3.05 m 

 B:-4.58 m 

 C:-6.04 m 

 D:-2.44 m 

 Correct Answer:- Option-B 

Question82:-How many days' notice is to be served to a consumer for disconnection of supply for non-payment of dues?

 A:-15 

 B:-7 

 C:-30 

 D:-10 

 Correct Answer:- Option-A 

Question83:-Which section of Electricity Act 2003, empowers formation of State Electricity Regulatory Commission  A:-82 

 B:-42 

 C:-62 

 D:-72 

 Correct Answer:- Option-A 

Question84:-Who appoints the Appellate Tribunal for Electricity? 

 A:-State Government 

 B:-State Electricity Regulatory Commission 

 C:-Central Government 

 D:-Central Electricity Regulatory Commission 

 Correct Answer:- Option-C 

Question85:-What is the maximum Contract Demand allowed for a consumer availing 33 kV supply?  A:-5000 kVA 

 B:-10000 kVA 

 C:-15000 kVA 

 D:-12000 kVA 

 Correct Answer:- Option-D 

Question86:-Who is the Appropriate Authority for implementing Quality control Orders for electrical goods in the State?  A:-State Electricity Regulatory Commission 

 B:-Secretary, Industries Department 

 C:-Chief Electrical Inspector 

 D:-Chief Secretary 

 Correct Answer:- Option-C 

Question87:-What is the maximum Contract Demand allowed for a consumer availing 110 kV supply?  A:-40000 kVA 

 B:-10000 kVA 

 C:-15000 kVA 

 D:-30000 kVA 

 Correct Answer:- Option-A 

Question88:-Which Section of Electricity Act 2003 contains provision for establishing National Load Despatch Centre?  A:-34 

 B:-39 

 C:-26 

 D:-56 

 Correct Answer:- Option-C 

Question89:-When an 11 kV line crosses a 110 kV line, what is the minimum clearance to be maintained?  A:-4.58 m 

 B:-3.05 m 

 C:-6.04 m 

 D:-2.44 m 

 Correct Answer:- Option-B 

Question90:-What is the maximum span allowed for a Low Voltage overhead line at a road crossing?  A:-65 m 

 B:-80 m 

 C:-70 m 

 D:-75 m 

 Correct Answer:- Option-A 

Question91:-What is the maximum number of full time members in Central Electricity Authority?  A:-6 

 B:-7 

 C:-9 

 D:-8 

 Correct Answer:- Option-D 

Question92:-What is the Average Service Availability Index (ASAI) for rural areas? 

 A:-97 

 B:-97.5 

 C:-98 

 D:-98.5 

 Correct Answer:- Option-B 

Question93:-What is the clearance above ground level for an HT overhead line across any street?  A:-5.5 m 

 B:-5.8 m 

 C:-6.1 m 

 D:-6.4 m 

 Correct Answer:- Option-C 

Question94:-Which is the IS for earthing practices? 

 A:-3646/1992 

 B:-7662/1974 

 C:-3043/1987 

 D:-8884/1978 

 Correct Answer:- Option-C 

Question95:-What is the permissible voltage drop at the end of a feeder cable? 

 A:-4% 

 B:-5% 

 C:-10% 

 D:-6%

 Correct Answer:- Option-B 

Question96:-How much is the approved power rating of a 16 A socket outlet? 

 A:-800 W 

 B:-1600 W 

 C:-500 W 

 D:-1000 W 

 Correct Answer:- Option-D 

Question97:-How many service tapings can be taken off a support of an LT overhead line?  A:-10 

 B:-6 

 C:-8 

 D:-4 

 Correct Answer:- Option-D 

Question98:-What is the clearance above ground level for an LT overhead line across any street?  A:-5.5 m 

 B:-6.1 m 

 C:-5.8 m 

 D:- 6.4 m 

 Correct Answer:- Option-C 

Question99:-How many times the normal current is the permissible starting current of a 7.5 kW motor?  A:-5 

 B:-3 

 C:-6 

 D:-4 

 Correct Answer:- Option-B 

Question100:-What is the minimum horizontal clearance for a building adjacent to a 66 kV line?  A:-2.3 m 

 B:-4.6 m 

 C:-1.2 m 

 D:-3.7 m 

 Correct Answer:- Option-A